Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
NPIAS - Answer Federal plan for airports, addresses development and planning on projects eligible for AIP. State Aviation System Plans - Answer more detailed on how airports within a state can meet states needs Metropolitan or Regional System Plans - Answer more specific indexable and consider capacity, intermodal access and local travelers Airport Areas - Answer Airside, Landside Landside - Answer intermodal access,parking, rental cars ticketing, bag claims, etc Airside Areas - Answer Runways, taxiways, fence, etc.
Typology: Exams
1 / 88
This page cannot be seen from the preview
Don't miss anything!
NPIAS - Answer Federal plan for airports, addresses development and planning on projects eligible for AIP. State Aviation System Plans - Answer more detailed on how airports within a state can meet states needs Metropolitan or Regional System Plans - Answer more specific indexable and consider capacity, intermodal access and local travelers Airport Areas - Answer Airside, Landside Landside - Answer intermodal access,parking, rental cars ticketing, bag claims, etc Airside Areas - Answer Runways, taxiways, fence, etc.
ALP-Grant Assurance 29 - Answer requires ALP be updated at all times, shows land, terminal and facilities. protection zones, approach areas, proposed development and unusual design features ALP Contents - Answer Standard ALP contains following: 1 Cover sheet-signature blocks, and location maps 2 ALP Sheet-data of existing and fyture airfield layout 3 Airport Layout Drawing 4 Airport Airspace Drawing-intended to show imaginary surfaces 5 Inner Portion of Approach Drawing-profile view of runway approaches and obstructions and surfaces associated with the Terminal Instrment Procedures (TERPS)
ALP is signed by FAA making it a legal document, drawings typically done with computer design software that link features on map with Geographic Information Systems (GIS), FAA uses eALP which allows sharing ALP data 5 Primary Functions of ALP - Answer 1 FAA approved plan required to receive AIP and PFC funding 2 blueprint for airport development 3 public document that serves as a record of aeronautical requirements 4 enables FAA and Sponsor to plan for future improvements 5 working tool for staff,
Notice of Propsed Construction or Alteration-FAA StNdard Form SF- 7460 - 1 - Answer notification of construction or alteration has to be given 30 days in advance Notice of Landing Area Proposal-Form SF- 7480 - 1 - Answer notification of activation or alteration of a landing area ALP - Answer ALP should be Reviewed and Vaidated every 2- 7 years. Necessary when existing ALP cannot accommodate forecast needs or meet design standards Grant Assurance Requirements for ALP - Answer 1 Property lines 2 location and nature of existing and proposed facilities (ie. runways, taxiway, parking lots)
FAA ALP 3 Levels of Approval - Answer Unconditional (met environmental processing), Conditional(environmental processing has not been completed for all items) and Mixed (completed elements can proceed others cannot until approval is received) National Environmental Policy Act (NEPA) - Answer review for environmental FAAs Airport Data and Information Program - Answer guides sponsors on collection, submission and management or airpirt data ensuring airport users most current information-achived through AIRPORT MASTER RECORD Airport Master Record - Answer describes basic operational and services data of the airports
Airport Data Record- 5010 Form - Answer Airport operator required to complete annually, FAA uses to complete aeronautical charts and Airport Facility Directory (A/FD) Airport Facility Directory (A/FD) - Answer pilots use as reference (runway lengths, Airport use, elevation and runway slope) Form 7460 Notice of Proposed Construction or Alteration-Part 157 Requirement - Answer required whenever there is proposed development Form 5010 and NOTAMS - Answer Pilits rely on information internet A/FD (provided on Form 5010). Temporary changes are issued as NOTAMS. NOTAMS can be cancelled when the information becomes part of the A/FD
Metropolitan (or Regional) Airport System Plan (MASP) & State Aviation System Planning (SASP) - Answer plan that asses how to integrate within the area, identifies role of each airport in the area and forecasts proposed future activities Airport Sysrem Planning 4 elements - Answer 1 system needs identification 2 system-wide development cost estimate 3 studies,surveys and other planning actions to decide which aeronautical needs will be met. 4 standards prescribed by state for development on non-primary public use airports Airport Master Plan - Answer primary document for long range planning. sets direction of development for an.
airport for up to 20 years, includes public involvement, FAA does not require that it has to be updated at certain time schedule but it is recommended (usually conducted every 8-15 years) Plans are completely tailored to individual airport, may be encouraged by ADO to receive funding for AIP projects. Goal of Master Plan - Answer provide framework for future development that is cost effective and satisfies the needs of the airport, market and community while balancing environmental and socioeconomic impacts. Sequenced into Airport Capital Improvement Plan and eligible for federal funding Master Plan is intended to produce - Answer 1 technical report- analysis conducted 2 summary report-facts, conclusions and recommendations 3 Updated ALP
reference "Guidelines to Selecting Airport Consultants". Consultant selection process is governed by the BROOKS ACT - requires selection be made based on qualifications and be awarded by fair and open selection process , consultants are usually hired before issuing RFPs, RFQs or Statements of Qualifications (SOQ). Process start with invitation to submit information via RFP or RFQ Topics addressed in Master Plan study - Answer 1 Goals and Objectives-why is MP study being conducted and key issues for future development
Classifications used in this element of Master Plan - Answer 1. Airfield/Airspace
Short-term (up to 5 years) near-term development, operational planing and environmental improvement. Medium-term- 6 - 10 year time frame used in planning capital improvements. Long-term-10+ years helpful for general planting. There are a number of forecasts including the OFFICIAL AIRLINE GUIDE (OAG) Aviation Deman Elements - Answer 1. Aircraft Operation (take off or landing)