The _________ consists of daily checks of the work to assure continuing compliance with contract requirements ✔✔Follow-up Phase Design-Build contracts require ✔✔The QC Manager to be in place and take an active role in the review and coordination of the design. Which of the following is included in all three phases of the Three Phases of Control? ✔✔Safety The purpose of Construction Quality Management is to ✔✔Achieve the quality established by properly developed requirements through the combined responsibility, but separate, efforts of contractors

Typology: Exams

2024/2025

Available from 01/05/2025

tizian-kylan
tizian-kylan 🇺🇸

2.7

(21)

3.7K documents

1 / 7

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Construction Quality Management for
Contractors Latest Update Graded A+
The _________ consists of daily checks of the work to assure continuing compliance with
contract requirements ✔✔Follow-up Phase
Design-Build contracts require ✔✔The QC Manager to be in place and take an active role in the
review and coordination of the design.
Which of the following is included in all three phases of the Three Phases of Control? ✔✔Safety
The purpose of Construction Quality Management is to ✔✔Achieve the quality established by
properly developed requirements through the combined responsibility, but separate, efforts of
contractors and government personnel
Testing is extremely important in construction quality management and is performed by ✔✔Both
the contractor and the government
pf3
pf4
pf5

Partial preview of the text

Download Construction Quality Management for Contractors Latest Update Graded A+ and more Exams Contract Law in PDF only on Docsity!

Construction Quality Management for

Contractors Latest Update Graded A+

The _________ consists of daily checks of the work to assure continuing compliance with contract requirements ✔✔Follow-up Phase

Design-Build contracts require ✔✔The QC Manager to be in place and take an active role in the review and coordination of the design.

Which of the following is included in all three phases of the Three Phases of Control? ✔✔Safety

The purpose of Construction Quality Management is to ✔✔Achieve the quality established by properly developed requirements through the combined responsibility, but separate, efforts of contractors and government personnel

Testing is extremely important in construction quality management and is performed by ✔✔Both the contractor and the government

The primary purpose of the Three-Phase Control System is to ✔✔Require the contractor to plan, schedule, and perform quality management actions to assure work meets all specified quality standards

Quality Assurance Personnel have the responsibility to ✔✔Require the contractor to maintain the quality specified in the plans and specifications

The _________________ is the appropriate time to assure that all materials and/or equipment have been tested, submitted, and approved ✔✔Preparatory Phase

The Preconstruction Conference and Coordination and Mutual Understanding Meeting Are ✔✔Conducted prior to the commencement of any physical construction work

Contractor testing procedures: ✔✔Are specified in the technical specs, outlined in the QCP, and addressed at Coordination and Mutual Understanding Meeting

The Quality Control Plan contains ✔✔Identification of individual quality quality control personnel, including name, qualifications, assigned duties, responsibilities and authorities.

The success or failure of all contractors is based upon ✔✔The ability to control costs, finance work, estimate jobs, schedule the work and maintain effective quality control

The contract requires the contractor to submit quality control reports ✔✔Daily

All submittals for government approval must be provided by the _________________ in time to allow for the review, approval, procurement, delivery, and performance of preparatory phase for an item before it is needed for construction. ✔✔Contractor to the Government

Partnering relationships are based upon ✔✔Building trust and dedication to common goals

ENG Form 4288-R, the submittal register: ✔✔Identifies those submittals identified in the contract and the corresponding submittal action codes

What is a purpose of the Coordination and Mutual Understanding Meeting? ✔✔The government and contractor meet to discuss implementation of the QC plan

Characteristics that describe a definable feature of work include: ✔✔Cross-referenced listings to the contractor's construction schedule that may have more than one definable feature under a section of the specifications

Requests for Information are submitted to ✔✔Ask for clarification of the contract

The ___________ is workmanship oriented, and where workmanship standards are established ✔✔Initial Phase

Grounds for withholding payment include the contractors failure to: ✔✔Perform in accordance with the terms of the contract, provide an acceptable QCP, and build to the quality standards established by the contract.

The contractor quality control organization: ✔✔May vary in size depending on the work being performed at a point in time.

A definable feature of work: ✔✔Can consist of a combination of multiple specification sections depending upon the nature of the work

Actual construction on the jobsite begins: ✔✔After an interim or final QC is accepted

Construction Quality Management is the performance of tasks, which ensure that construction is performed: ✔✔According to plans and specifications, on time, within a defined budget and a safe work environment

A cumulative list of job deficiencies/rework items can be found in: ✔✔A deficiency tracking system/reworks items list that is typically maintained in RMS

Inspection is: ✔✔The process by which ongoing and completed work is examined

It is the responsibility of Quality Assurance Personnel to: ✔✔Periodically verify that the contractor's system of control is working effectively