AX5 Costos y Presupuestos: Exercises and Calculations for Cisterna Construction, Study notes of History of Yugoslavia

A series of exercises and calculations related to the construction of a cistern. It includes detailed breakdowns of materials, quantities, and dimensions for various components, such as the foundation, walls, and reinforcement. Practical examples of cost estimation and material planning for civil engineering projects.

Typology: Study notes

2021/2022

Uploaded on 03/19/2025

juan-mendez-oy0
juan-mendez-oy0 🇺🇸

1 document

1 / 13

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
MATERIA: AX5 Costos y Presupuestos GRUPO:
NOMBRE DEL ALUMNO:
Montalvo Mendez Juan Cralos
Generadores: Cisterna
NUM. DE CONTROL: 22360454
FECHA:
13 de octubre 2024
CONCEPTO LOCALIZACION LARGO ANCHO ALTO PZAS RESULTADO UNIDAD
OBSERVACIONES
EJE TRAMO TIPO
A-D 9 _10 0.8 0.40 0.08 14 0.3584
Total Demo-001 = 0.3584 m²
A-D 9 _10
Total Reti-001 = 2.808 m³
A-D 9 _10 6 7.20 - 1 43.20
CISTERNA
A-B 9_10 2.44 2.44 2.40 1
14.2886
A-B 9_10 Total de Exca-001 = 14.289 m³
Total de RETI-002 = 18.56 m³
Demo-001 Demolision de
piso con concreto simple
Reti-001 Retiro de escombro
producto de la demolicion
mas 30% por concepto de
abundamiento
=0.648 m³
Traz-001 Trazo y nivelacion
del terreno
Exac-001 excavacion con
material tipo B a una
profundidad de 2.00 a 4.00
m
Reti-001 Retiro de material
producto de excavacion mas 30% por acarreo de abundamiento
=4.28m^2
pf3
pf4
pf5
pf8
pf9
pfa
pfd

Partial preview of the text

Download AX5 Costos y Presupuestos: Exercises and Calculations for Cisterna Construction and more Study notes History of Yugoslavia in PDF only on Docsity!

MATERIA: AX5 Costos y Presupuestos GRUPO: NOMBRE DEL ALUMNO: Montalvo Mendez Juan Cralos Generadores: Cisterna NUM. DE CONTROL: 22360454 FECHA: 13 de octubre 2024 CONCEPTO LOCALIZACION LARGO ANCHO ALTO PZAS RESULTADO^ UNIDAD OBSERVACIONES EJE TRAMO TIPO A-D 9 _10 0.8 0.40 0.08 14 0.3584 m² Total Demo-001 = 0.3584 m² A-D 9 _ Total Reti-001 = 2.808 m³ A-D 9 _10 6 7.20 - 1 43.20 m² CISTERNA A-B 9_10 2.44 2.44 2.40 1 14.2886 m³ A-B 9_10 Total de Exca-001 = 14.289 m³ Total de RETI-002 = 18.56 m³ Demo-001 Demolision de piso con concreto simple Reti-001 Retiro de escombro producto de la demolicion mas 30% por concepto de abundamiento =0.648 m³ Traz-001 Trazo y nivelacion del terreno Exac-001 excavacion con material tipo B a una profundidad de 2.00 a 4. m Reti-001 Retiro de material producto de excavacion (^) mas 30% por acarreo de abundamiento =4.28m^

c dez Juan Cralos tubre 2024 OBSERVACIONES

MATERIA: AX5 Costos y Presupues GRUPO: (^) c NOMBRE DEL ALUMNO: Jose Ubaldo Rodriguez Hernandez Generadores: Cisterna NUM. DE CONTROL: 22360492 FECHA: 13 de octubre 2024 CONCEPTO LOCALIZACION LARGO ANCHO ALTO PZAS UNIDAD OBSERVACIONES EJE TRAMO TIPO A-B 9 _10 1.50 4 6 m A-B 9 _10 1.

A-B 9 _10 1.50 2.00 4 12.00 m A-B 9 _10 1.50 2.00 4 12.00 m² A-B 9_10 1.50 2.00 4 12.00 m 1.50 1.50 2 4.50 m² 16.50 m² RESULTADO Cade-002 Cadena de cerramiento de 1715 cm con f´c=200 kg/cm² Ag. Max 3/4" R.Permeable Cade-003 Cadena de cerramiento de 1715 cm con un f´c=200 kg/cm² Ag. Max 3/4" R.Permeable Rebo-001 Rebocado con mortero en p.o.p. cem-are 0.005- Repe-001 Repellado fino en muro en mortero cem,fergral-arena pop 1- Pint-001 suministro y aplicación de pintura para cisterna Comex incluye sellador y 3 capas Loza-001 Loza reticular de 0.25 de peralte f´c= 200 kg/cm² Ag. Max. 3/4" R: Permeable con Ø3/4" y grapas 3/4" @ 15cm

MATERIA: AX5 Costos y Presup GRUPO: (^) c NOMBRE DEL ALUMNO: Jose Ubaldo Rodriguez Hernandez Generadores: Cisterna NUM. DE CONTROL: 22360492 FECHA: 13 de octubre 2024 CONCEPTO LOCALIZACION LARGO No. DE 2 (14") 3(3/8") 4(1/2") 5(5/8") 6(3/4") 8(1") EJE TRAMO VARILLAS^ ELEMENTOS^ 0.25 0.557 0.996 1.56 2.25 3. A-B 9 _10 2.12 2.12 26.00 55.12 m Ganchos y dobleces Ø1/2 = 0. 26Ø (0.0127) = 0.3302 m Longitud de la barra - A= 0.3202+ 1.79 = 2. Numero de piezas 1.79 / 0.15 = 11.93 = 12 por 2 lados = 13*2 = 26 pzas TOTAL DE ESTA HOJA (METROS LINEALES) PESO DE VARILLA POR METRO LINEAL 0.250 0.557 0.996 1.560 2.250 3. TOTAL DE ESTA HOJA EN KILOGRAMOS. 54. Acer-001 Habilitado y armado refuerzo fý=4200 kg/cm² con Ø 1/2" en cimentacion @ 15cm c.a.c.

MATERIA: AX5 Costos y Presupues GRUPO: (^) c NOMBRE DEL ALUMNO: Jose Ubaldo Rodriguez Hernandez Generadores: Cisterna NUM. DE CONTROL: 22360492 FECHA: 13 de octubre 2024 CONCEPTO LOCALIZACION LARGO No. DE 2 (14") 3(3/8") 4(1/2") 5(5/8") 6(3/4") 8(1") EJE TRAMO VARILLAS^ ELEMENTOS^ 0.25 0.557 0.996 1.56 2.25 3. A-B 9 _10 20.37 16.00 32.59 m Ø3/8" = 0.0095 (^) A-B 9 _10 0.7332 48 33. ganchos y dobleces (26Ø)(0.0095) = 0.247 - B= 0.247+1.78=2. N. piezas 4*4 extremos = 16 pzas D 1/4" = 0. Ganchos y dobleces (13Ø) (0.0064) = 0.0832 m C= 0.0832+0.10+0.225+0.10+0.25=1. Nuemero de piezas= (0.26)=11+1 = 12 Total 4 extremos = 12 = 48 pzas TOTAL DE ESTA HOJA (METROS LINEALES) PESO DE VARILLA POR METRO LINEAL 0.250 0.557 0.996 1.560 2.250 3. TOTAL DE ESTA HOJA EN KILOGRAMOS 8.79 kg 18. Habilitado y armado con acero fý=4200 kg/cm² R.N varilla N´3 (3/8) en cimentacion cadena de desplante 4Ø3/8 peralte Habilitado y armado fý= 4200 kg/cm² N. alambron 1/8" en cimentacion cadena de desplante estribo @ 15 cm

MATERIA: AX5 Costos y Presupues GRUPO: (^) c NOMBRE DEL ALUMNO: Jose Ubaldo Rodriguez Hernandez Generadores: Cisterna NUM. DE CONTROL: 22360492 FECHA: 13 de octubre 2024 CONCEPTO LOCALIZACION LARGO No. DE 2 (14") 3(3/8") 4(1/2") 5(5/8") 6(3/4") 8(1") EJE TRAMO VARILLAS^ ELEMENTOS^ 0.25 0.557 0.996 1.56 2.25 3. A-B 9 _10 2.522 16 40.37m Ø3/8= 0. POR GANCHOS Y DOBLECES 26Ø(0.0095)= 0. D= 0.247 + 2.275=2.522 (^) - Numero de piezas 4pzas * 4 castillos = 16 pzas A-B 9_10 0.483 60 28.98m Ø1/4= 0. Por ganchos y dobleces (15Ø)(0.0064)=0. E=0.83+0.10+0.10+0.10+0.10=0.483m N. piezas 20/0.15= 13.3 piezas = 14 +1= 15 pzas 154=60 pzas TOTAL DE ESTA HOJA (METROS LINEALES) PESO DE VARILLA POR METRO LINEAL 0.250 0.557 0.996 1.560 2.250 3. TOTAL DE ESTA HOJA EN KILOGRAMOS 7.24 kg 22. Habilitado y armado de refuerzo fý=4200 kg/cm² con varillas N´ (3/8") en cimentacion castillo de 15 Habilitado y armado de acero de refuerzo fý= 4200 kg/cm² con alambron del N´2 (1/4") en cimentacion en cadena de desplante 0.15*0.30 m

MATERIA: AX5 Costos y Presupues GRUPO: (^) c NOMBRE DEL ALUMNO: Jose Ubaldo Rodriguez Hernandez Generadores: Cisterna NUM. DE CONTROL: 22360492 FECHA: 13 de octubre 2024 CONCEPTO LOCALIZACION LARGO No. DE 2 (14") 3(3/8") 4(1/2") 5(5/8") 6(3/4") 8(1") EJE TRAMO VARILLAS^ ELEMENTOS^ 0.25 0.557 0.996 1.56 2.25 3. A-B 9 _10 1.73 16 27. Ø 3/8"= 0. Ganchos y dobleces (26Ø)(0.0095) = 0.247 m H=0.247+1.49= 1.73 m (^) - Numero de piezas (4pzas)(4extremos)=16 pza A-B 9 _10 0.6832^48 32.79m Ø2(1/4")=0. ganchos y dobleces (13Ø)(0.0064)m=0. I=0.083+0.10+0.20+0.10+0.20=0.6832 m Numero de piezas 1.54/0.15=10.26pza=11 pza + 1= (12)(4 cadenas)= 48 piezas TOTAL DE ESTA HOJA (METROS LINEALES) PESO DE VARILLA POR METRO LINEAL 0.250 0.557 0.996 1.560 2.250 3. Habilitado y armado de acero de refuerzo fy=4200 kg/cm² con varillas #(3/8") en cadena de cimentacion de 0.15*0.25 m Habilitado y armado de acero de refuerzo fy=4200 kg/cm² en estribos de cerramiento de @15cm

MATERIA: AX5 Costos y Presupuest GRUPO: (^) c NOMBRE DEL ALUMNO: Jose Ubaldo Rodriguez Hernandez Generadores: Cisterna NUM. DE CONTROL: 22360492 FECHA: CONCEPTO LOCALIZACION LARGO No. DE 2 (14") 3(3/8") 4(1/2") 5(5/8") 6(3/4") 8(1") EJE TRAMO VARILLAS^ ELEMENTOS^ 0.25 0.557 0.996 1.56 2.25 3. A-B 9 _10 2.1202 12 25. Ø1/2" = 0. Ganchos y dobleces (26Ø)(0.0127) = 0.3320 m D=0.3320+1.79= 2. Numero de piezas (^) - (2pzas*nervio)(3nervio)(2extremos)=12 pza A-B 9_10 0.466 7.202^ 32.112m Ø#3(3/8") = 0. ganchos y dobleces (26)(0.0095)= 0. K= 0.266+0.20=0. Numero de piezas 1.54/0.15= 10.26= 11 pza +1 = 12pza (3)=(36 pza)(2extremos)=72 pzas TOTAL DE ESTA HOJA (METROS LINEALES) PESO DE VARILLA POR METRO LINEAL 0.250 0.557 0.996 1.560 2.250 3. TOTAL DE ESTA HOJA EN KILOGRAMOS 17.88 kg 25.34 kg Habilitado y armado de acero f ´y=4200 kg/cm² en losa reticular veradura 2Ø por nervio Habilitado y armado de acero f'y=4200 kg/cm² con Ø3/8" en ganchos para losa reticular 2 pza @15cm