Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Foreman Certification Practice Test: Questions and Answers, Exams of Nursing

A comprehensive set of practice questions and answers for foreman certification. it covers various aspects of foreman responsibilities, including safety, negotiation, project management, and blueprint reading. The questions are designed to test knowledge and problem-solving skills essential for successful foreman certification. the detailed answers offer valuable insights into best practices and industry standards.

Typology: Exams

2024/2025

Available from 04/24/2025

alekii-mmanyi
alekii-mmanyi 🇺🇸

288 documents

1 / 13

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Foreman Certification Practice Test
QUESTIONS WITH 100% CORRECT
ANSWERS!!
If a foreman from a different trade approaches you claiming that one of your crew
members has been injured while working outside of his scope of work, what would be
the FIRST action you should take? - CORRECT ANSWER-Get the crew
member medical attention.
Which of the following is a true statement with respect to a foreman 's responsibility
related to his or her crew? - CORRECT ANSWER-The foreman is
responsible for anything that occurs at the jobsite from the beginning of the work
day/shift to the end of the work day/shift.
Why is preparation so important in a negotiation? - CORRECT ANSWER-
Having time to prepare and having a plan makes it easier to keep emotions in check.
The piping specifications required all wall penetrations to have a steel pipe sleeve.The
steam piping size is 4 inches SCH 80 carbon steel with 1 inch of fiberglass insulation.
What diameter of SCH 40 carbon steel sleeve is the minimum that you can use? -
CORRECT ANSWER-8 inches
A member of your crew is being excessively loud and using inappropriate language. As
a foreman, what is the MOST effective course of action to take? - CORRECT
ANSWER-Explain to them that their behavior is inappropriate and may be
considered harassment by fellow crew members and by management
What is the purpose of a separation notice? - CORRECT ANSWER-The
purpose of a separation notice is to identify the circumstances surrounding a
termination.
With which of the following costs should a foreman be MOST concerned? -
CORRECT ANSWER-Labor
pf3
pf4
pf5
pf8
pf9
pfa
pfd

Partial preview of the text

Download Foreman Certification Practice Test: Questions and Answers and more Exams Nursing in PDF only on Docsity!

Foreman Certification Practice Test

QUESTIONS WITH 100% CORRECT

ANSWERS!!

If a foreman from a different trade approaches you claiming that one of your crew members has been injured while working outside of his scope of work, what would be

the FIRST action you should take? - CORRECT ANSWER -Get the crew

member medical attention. Which of the following is a true statement with respect to a foreman 's responsibility

related to his or her crew? - CORRECT ANSWER -The foreman is

responsible for anything that occurs at the jobsite from the beginning of the work day/shift to the end of the work day/shift.

Why is preparation so important in a negotiation? - CORRECT ANSWER -

Having time to prepare and having a plan makes it easier to keep emotions in check. The piping specifications required all wall penetrations to have a steel pipe sleeve.The steam piping size is 4 inches SCH 80 carbon steel with 1 inch of fiberglass insulation. What diameter of SCH 40 carbon steel sleeve is the minimum that you can use? -

CORRECT ANSWER -8 inches

A member of your crew is being excessively loud and using inappropriate language. As

a foreman, what is the MOST effective course of action to take? - CORRECT

ANSWER -Explain to them that their behavior is inappropriate and may be

considered harassment by fellow crew members and by management

What is the purpose of a separation notice? - CORRECT ANSWER -The

purpose of a separation notice is to identify the circumstances surrounding a termination. With which of the following costs should a foreman be MOST concerned? -

CORRECT ANSWER -Labor

A(n) ________________ occurs when any condition or document modifies the work as

defined in the contract documents during the bidding process. - CORRECT

ANSWER -Change Order

On a project that requires 100% tie-off for elevated work, how many lanyards are

required on a full body harness? - CORRECT ANSWER -

The client is not happy with part of the project and wants to make a change. What actions should you take to ensure the client is happy while ensuring that progress on

your job continues? - CORRECT ANSWER -Stop working on that portion of

the job that is at issue and contact your supervisor.

Using drawing, what is the elevation of the top of the 24 x 18 duct? - CORRECT

ANSWER -31 feet and 10 inches.

On the project blueprint there is a bank of four pipe runs with each pipe measuring three inches in diameter which measure 12 inches in length on the blueprint. The scale used on the blueprint is 1/4 inch equals 1 foot. How many feet of 3 inch pipe should be

ordered to complete the runs? - CORRECT ANSWER -192 feet

Using the formula below, what is the correct 45 offset when you have a rolling offset where the roll is 8 inches and the rise is 6 inches? Formula: Offset = roll 2 + rise2 -

CORRECT ANSWER -10 inches.

What is the first rule of negotiation? - CORRECT ANSWER -Understand the

other person's needs. Assume that you need to purchase 1,000 feet of pipe for your assigned project. If pipe costs $1.25 per foot, what is the cost of purchasing 40% of the total pipe needed? -

CORRECT ANSWER -$

Which of the following describes the purpose of "Short Interval Planning? " or "Look

Ahead Planning"? - CORRECT ANSWER -Breaking the job into small

manageable pieces. Which of the following correctly identifies what is included in legitimate labor costs? -

CORRECT ANSWER -Hourly wages, fringe benefit packages, payroll taxes,

insurance and safety costs,and small tools and consumables.

Where can the requirements for "Job Close Out" be found? - CORRECT

ANSWER -Within the contract documents

In which of the following documents may be found the most complete listing of

hazardous chemicals that might be encountered on the jobsite? - CORRECT

ANSWER -American National Standards Institute hazardous substances appendix

When is the best time to begin planning for close-out of a job? - CORRECT

ANSWER -at the beginning of the job.

Using drawing what is the dimension of DIM "W"? - CORRECT ANSWER -

feet and 10 inches.

What is pre-construction planning? - CORRECT ANSWER -Developing a job

strategy before the job begins. When working in locations high off of the ground, the area below should be: -

CORRECT ANSWER -All of the above

Positive motivation should include such practices as: - CORRECT

ANSWER -Praising workers for a job well done.

What percent of the UA will be eligible to retire before 2027? - CORRECT

ANSWER -55%

Which statement about conflict is NOT true? - CORRECT ANSWER -Conflict

must always be resolved. What standard is applied with respect to the abuse of substances on the jobsite? -

CORRECT ANSWER -A zero tolerance policy has been established by the

United Associations and it is applied to all locals.

Which of the following is NOT required on a daily log? - CORRECT

ANSWER -Weather conditions on the day of the log entry.

Does the Civil Rights Act apply to your work area. - CORRECT ANSWER -

Yes

If a straight run travels through 5 rooms and each room is 80 feet long, how many feet

of pipe would be needed to span the distance? - CORRECT ANSWER -

feet Suppose you have a crew member who was late this morning for the 2nd time this week. What would be the MOST appropriate step to take with this crew member? -

CORRECT ANSWER -Meet with the crew member in private and issue a

warning.

How long should short interval planning tasks be? - CORRECT ANSWER -

No more than 10 days Which of the following should you, as a foreman, NOT allow an OSHA inspector to do

on a job site? - CORRECT ANSWER -Walk around the job site

unaccompanied Which of the following items is NOT one of the MINIMUM personal protective equipment

requirements on the job? - CORRECT ANSWER -Ear plugs.

What "Personal Protective Equipment" should be used when operating a gasoline

powered abrasive saw? - CORRECT ANSWER -All of the above

While creating the rough layout for a piping project, you discover a problem with the 2" Hot Water Supply and Hot Water Return piping. By following the design specifications you determine that these pipes will be interfering with the sheet metal subcontractor's 48" duct work. Which of the following actions should the Piping Foreman take? -

CORRECT ANSWER -Report the interference to your project manager.

When a "routing conflict" occurs between coordinated trades what strategy should be

applied to resolve the conflict? - CORRECT ANSWER -Request information

from the engineer on how progress should proceed. What would be the FIRST step that should be taken after observing a pipe that is

dripping liquid in a chemical factory? - CORRECT ANSWER -Barricade off

the area. When is the BEST time for a foreman to hold information sharing "Toolbox SafetyTalks:

" - CORRECT ANSWER -Regularly on a weekly basis to address safety

issues and learn about new tools or materials.

c. list materials. d. call for availability and prices. What is the proper order or sequence of these steps? -

CORRECT ANSWER -b, c, d, a

You have an apprentice on your project that is struggling to do their job. What is

theBEST approach to helping them? - CORRECT ANSWER -Have them

work with an experienced journeyman. If a confined space is shown to be oxygen deficient, which of the following should you

do? - CORRECT ANSWER -Purge with fresh air.

What is the difference between a CBA and a Job Specific labor agreement? -

CORRECT ANSWER -All of the above

A pipe has a 9 foot above finished floor (AFF) center line elevation and a benchmark that is 2 feet above finished floor (AFF). What is center line of the pipe above

benchmark? - CORRECT ANSWER -7 feet

Which of the following is NOT considered a direct job cost? - CORRECT

ANSWER -Home office overhead.

During the course of a project you have noticed that there is a greater than normal number of Change Orders being submitted. Which of the following is the MOST

important step that you need to take? - CORRECT ANSWER -Maintain an

accurate Job Log in case specific questions are asked about why the project was completed in the way it was Which of the following prohibits discrimination based on gender, race, or national origin?

  • CORRECT ANSWER -The Civil Rights Act. (Refer to Figure 1 when answering this question.) A pipe needs to come up in the wall

marked *. How far is the center of the wall from column line? "C? "? - CORRECT

ANSWER -5 feet and 9 inches.

After piping a water system, what is the FIRST step that should be taken? -

CORRECT ANSWER -Test

You observe a crew member whose behavior is strange and unpredictable on the

jobsite. What is the FIRST thing you, as a foreman, should do? - CORRECT

ANSWER -Approach the crew member and try to determine the cause of the

strange behavior.

Using drawing, what length is dim "G" - CORRECT ANSWER -11 feet and 0

inches. What should a foreman do if damage to a shipment is discovered AFTER the delivery

driver has left the job site? - CORRECT ANSWER -Notify the Project

Manager and note the damage on the daily log Which of the following represents an effective way to ensure that the job is progressing

within the allotted budget? - CORRECT ANSWER -Keep a log of man hours

used and compare it to the percentage of the job completed Under which conditions do most contracts indicate changes to the work are valid? -

CORRECT ANSWER -Signed change order authorizing the scope and price

A blueprint is written with a scale of 1/4 inches equals 1 foot. A room scales out to 15

1/4inches. How many feet would the room be? - CORRECT ANSWER -

feet Two mechanical contractors are working on a common steam line. Who is responsible

for lock out/tag out? - CORRECT ANSWER -Each individual working on the

steam line

What is the purpose of a "Separation Notice? " - CORRECT ANSWER -To

identify the circumstances surrounding a termination One of your crew members is a highly experienced journeyman who only wants to "do things their own way." As a foreman, what is the BEST effective way to handle this

worker? - CORRECT ANSWER -Listen to their ideas but make the final

decision on how to proceed yourself. "Footing Drain: Furnish and install 4 inch drain tile or other type of material approved by local code authority. The contractor is to furnish and place gravel in accordance with requirements of local code authority. "According to the information above, which of the

following is the MOST accurate statement? - CORRECT ANSWER -Footing

drains shall be 4 inches.

What size sleeve is needed for a 6 inch schedule 10 pipe with 2 inches of insulation? -

CORRECT ANSWER -12 inches

If an OSHA inspector comes to your jobsite, what is one thing you should not let him/her

do? - CORRECT ANSWER -Walk around the job site alone

Certain steps are typically followed when starting a job. Among those listed below, which of the following options correctly identifies the order these steps should be

completed? - CORRECT ANSWER -Sketch, layout, order material, install.

In an average 8-hour day on a construction site what percentage is spent on direct

installation? - CORRECT ANSWER -32%

Assume a project blueprint is written with a scale of 1/4 inch = 1 foot. Using a ruler,you determine that 6 inches of pipe must be ordered (as measured on the blueprint? 'sscale). How many actual feet of pipe must be ordered to complete the project? -

CORRECT ANSWER -24 feet

You have 35 pipe hangers for a job that requires 40 hangers. However for the job to proceed, the pipe needs to be hung as soon as possible. What should you do? -

CORRECT ANSWER -Hang as much pipe as you can until more hangers

arrive. (Refer to Figure 1 when answering this question.) A pipe needs to come up in the wall

marked. How far is the center of the wall from column line "D " - CORRECT

ANSWER -35 feet and 9 inches.

If it becomes necessary for a foreman to discipline an employee, which of the following

is the BEST way to handle it? - CORRECT ANSWER -Meet privately with the

employee and his or her job steward. A "Log Book " or "Job Log " is the most appropriate place to document which of the

following? - CORRECT ANSWER -The events that occurred on the jobsite

each day. "Provide all pipe passing through footings, floors, slabs, and masonry walls with steel pipe sleeves, the inside diameter of which shall be at least -inch greater than the outside diameter of the pipe and covering passing through it. Sleeves in exterior walls, slabs on earth, or in any slab which may be wet (after completion of the building) shall be Schedule 40 PVC pipe and shall have the space between the pipe and the sleeves

caulkedwatertight."According to the paragraph above, which of the following does NOT

apply? - CORRECT ANSWER -A 4 inch pipe sleeve is sufficient for a 4 inch

inside diameter pipe to passthrough a masonry wall. Which of the following best illustrates the PRIMARY role of a foreman? -

CORRECT ANSWER -To effectively manage and lead the crew.

You notice a conflict between two workers in your crew. What would be the MOST

appropriate course of action to follow? - CORRECT ANSWER -Talk to the

individuals and try to resolve the issue.

Using drawing what is "Elevation A? " - CORRECT ANSWER -43 feet and 6

inches If your project has a productivity factor of .80, what does this indicate? -

CORRECT ANSWER -At the present time, your project is 20% below budget.

A member of your crew has come to you complaining that they are being harassed by another crew member. What is the FIRST step that you, as a foreman, should take? -

CORRECT ANSWER -Document the event and bring it to the attention of

supervisors. On average, what percentage of a message's impact comes from the words you say? -

CORRECT ANSWER -7 %

Which of the following locations represents the BEST place to store jobsite materials in

a manner that enhances productivity? - CORRECT ANSWER -As close to the

point of installation as possible

What is the foreman's primary responsibility? - CORRECT ANSWER -To

supervise and lead a group of workers. The 45-degree offset is one of the most widely used formulas in layout. What is the

formula for figuring this offset? - CORRECT ANSWER -None of the above.

As a foreman, what should ALWAYS be your FIRST priority when planning for a job? -

CORRECT ANSWER -Ensuring the safety of your crew and others on the

jobsite.

When is it appropriate to include your subcontractors in jobsite meetings? -

CORRECT ANSWER -All of the above

"Provide all pipe passing through footings, floors, slabs, and masonry walls with steel pipe sleeves, the inside diameter of which shall be at least 1/2-inch greater than the outside diameter of the pipe and covering passing through it. Sleeves in exterior walls, slabs on earth, or in any slab which may be wet (after completion of the building) shall be Schedule 40 PVC pipe and shall have the space between the pipe and the sleeves caulkedwatertight."According to the paragraph above, when installing a sleeve in a

poured slab roof what type of material should be used? - CORRECT

ANSWER -SCH. 40 PVC.

There are guidelines for installing the correct size of septic tank. Septic tanks shall have a minimum size of 1,500 gallons. If a larger size is required by local authorities, the contractor shall comply with local codes but allow in his or her bid for the cost associated with such increase in size. According to the paragraph above, who is

responsible for installing the correct sized septic tank? - CORRECT

ANSWER -Contractor.

Using drawing, what is the elevation of the waste line below the sub-basement floor? -

CORRECT ANSWER --4 feet and 6 inches.

You and your crew of three journeymen started a job on Thursday and finished the job on the following Tuesday. No work was completed on Sunday. The first day you and your crew worked 10 hours. On all other days you and your crew worked 8 hours each day. Assume that all hours worked in excess of 8 hours are counted as overtime and that all overtime is counted as time-and-a-half. What is the total number of hours paid? -

CORRECT ANSWER -188 hours paid

What is the most common reason for back charges? - CORRECT ANSWER -

Clean up Which of the following is NOT a primary purpose of a Material Safety Data Sheet

(MSDS)? - CORRECT ANSWER -To provide instructions for use of a

chemical. As a general rule, when is the BEST time for a foreman to schedule effective meetings

with their work crew? - CORRECT ANSWER -At the beginning of a shift