GCSS Exam
With
Complete
Solution Latest
Update 2023
Assured A+
- When creating an OBSL work order, the 4 low priority
list item is selected. - Correct answer b. FALSE
- When a change is made to the OBSL BOM, a new XML file is received into GCSS-Army via the ______, which results in an update to the existing OBSL BOM. - Correct answer d. SAP Business Workplace
- The intent of the OBSL work order is to be able to compare the OBSL material requirement quantities with the ______. - Correct answer a. On-hand material quantities
- The nomenclature for the OBSL work order description is the OBSL, followed by the watercraft vessel ______. - Correct answer c. Advanced
Shipment Notification (ASN) Number
- True or False? The OBSL work order is not to be released. - Correct answer a. TRUE
- The OBSL work order that is created for a watercraft mission is used for material replenishment. - Correct answer b. FALSE
safety stock requirements. - Correct answer a. TRUE
- The ______ transaction is used to create the OBSL/On-Hand Material Quantities spreadsheet. - Correct answer d. Equipment Status Report (Z_EQUST)
- The ______ transaction is used to display the open watercraft OBSL work order.
- Correct answer a. Equipment Situation Report (/ISDFPS/DISP_EQU_SIT)
- The ______ transaction is used to create the watercraft OBSL work order.
- Correct answer b. Create Order (IW31)
- Operators are entered into a ground equipment dispatch where as ______
- True or False? The equipment usage reading is applied to the end item equipment and to the engine and transmission in a ground equipment dispatch and to only the end item in a watercraft equipment dispatch. - Correct answer a. TRUE
- True or False? Equipment usage readings
are tracked for the crew members in a watercraft equipment dispatch. - Correct answer b. FALSE
- The ______ transaction is used to display the Functional Location Structure for a piece of watercraft equipment. - Correct answer a. Equipment Situation Report (/ISDFPS/DISP_EQU_SIT)
of equipment that requires usage to be tracked and that is installed in a watercraft Functional Location Structure. - Correct answer a. TRUE