Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Economic Duress in Construction: Identifying Illegitimate Commercial Pressure, Lecture notes of Construction

The concept of economic duress in the construction industry, focusing on cases where one party uses commercial pressure to force an unfavourable deal. The article discusses the denning approach, specific examples of economic duress in construction cases, and the recent supreme court decision in times travel. It also touches upon the limitations of lawful act duress.

What you will learn

  • What is economic duress in construction?
  • What are the limitations of lawful act duress in construction?
  • How does the Denning approach apply to economic duress in construction?

Typology: Lecture notes

2021/2022

Uploaded on 09/12/2022

mdbovary
mdbovary 🇬🇧

4.8

(8)

215 documents

1 / 4

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Authors/Presenters
Im going to make him an offer he cant refuse, was Vito
Corleones favourite negotiating tactic. While his methods are a far
cry from how things are done in the construction industry,
commercial pressure can be used to force a party to accept an
unfavourable deal. When does such behaviour cross the line and
become
illegitimate pressure or duress
? Is it where a party,
possibly a monopoly, tells the other it will never deal with it again
unless it gives up all its claims? That is the situation that
the
Supreme Court looked at recently
but it is worth looking at how
this works in a construction context.
The Denning approach
If you are the sort of person who asks What would Lord Denning do?,
D&C Builders Ltd v Rees [1966]
2 QB 617
is a good example of his approach to construction disputes. The claimant contractor was a
company made of two individuals, a decorator and a plumber, and the defendant had a shop where he
sold builders’ materials. The contractor pressed for months for a debt of £482 13s 1d to be paid, only to
be told by the defendants wife, who knew they were in financial difficulties, they could agree to be paid
£300 in settlement of the debt or they would get nothing. They accepted payment but then sued for the
balance.
The case raised interesting issues about consideration and estoppel but Lord Denning MR made it clear
that while a genuine settlement would be enforceable, this was not the case where this would be
inequitable and undue pressure was being placed by threatening to break the contract (by paying
nothing) to compel the creditor to do what it was unwilling to do. As he put it:
Shy Jackson
Partner
London
shy.jackson@bclplaw.com
October 8, 2021
Hobsons choice, the latest on economic
duress
Page 1 of 4
pf3
pf4

Partial preview of the text

Download Economic Duress in Construction: Identifying Illegitimate Commercial Pressure and more Lecture notes Construction in PDF only on Docsity!

“I’m going to make him an offer he can’t refuse”, was Vito Authors/Presenters

Corleone’s favourite negotiating tactic. While his methods are a far cry from how things are done in the construction industry, commercial pressure can be used to force a party to accept an unfavourable deal. When does such behaviour cross the line and become illegitimate pressure or duress? Is it where a party, possibly a monopoly, tells the other it will never deal with it again unless it gives up all its claims? That is the situation that the Supreme Court looked at recently but it is worth looking at how this works in a construction context.

The Denning approach

If you are the sort of person who asks “What would Lord Denning do?”, D&C Builders Ltd v Rees [1966] 2 QB 617 is a good example of his approach to construction disputes. The claimant contractor was a company made of two individuals, a decorator and a plumber, and the defendant had a shop where he sold builders’ materials. The contractor pressed for months for a debt of £482 13s 1d to be paid, only to be told by the defendant’s wife, who knew they were in financial difficulties, they could agree to be paid £300 in settlement of the debt or they would get nothing. They accepted payment but then sued for the balance.

The case raised interesting issues about consideration and estoppel but Lord Denning MR made it clear that while a genuine settlement would be enforceable, this was not the case where this would be inequitable and undue pressure was being placed by threatening to break the contract (by paying nothing) to compel the creditor to do what it was unwilling to do. As he put it:

Shy Jackson

Partner London shy.jackson@bclplaw.com

October 8, 2021

Hobson’s choice, the latest on economic

duress

“No person can insist on a settlement procured by intimidation.”

This was the background to the doctrine of economic duress, where it is necessary to show causation and that the effect of the pressure is that there is no practical alternative. But the biggest difficulties have concerned the need to identify what amounts to illegitimate commercial pressure.

It’s all about the facts

It always helps to look at specific examples when considering general principles. In Williams v Roffey Bros and another , a sub-contractor asked for more payments, knowing the main contractor would otherwise be exposed to delay damages. The Court of Appeal considered duress but noted there was no finding of duress on the facts as it was the main contractor who offered to pay the additional sum. But the opposite conclusion was reached on similar circumstances in another construction case 12 years later in Carillion Construction Ltd v Felix (UK) Ltd [2001] BLR 1.

Here the cladding sub-contractor threatened to stop supplies unless the final account was agreed at the amount claimed. A note disclosed by the sub-contractor stated under “Carillion weaknesses” that “[t]hey need to finish the work” and “[n]o deliveries until we get agreement”.

The judge held that the pressure applied by the sub-contractor was illegitimate, relying on the fact it knew there was a number of trades that were dependent on the cladding works, that Carillion could not complete the main contract works without the cladding and that it would be impossible to find an alternative supplier in time.

It is not only sub-contractors who sometimes take advantage of their position. In Adam Opel GmbH, Renault SA v Mitras Automotive (UK) Ltd , it was Mitras, Opel’s sole supplier of a mount for the front bumper who, when given a valid six months’ notice of termination, demanded to be paid compensation and threatened to suspend supplies until this was agreed.

When Opel realised they only had 24 hours’ worth of supplies remaining and that the potential losses could be substantial (and having failed to obtain an injunction), it agreed to Mitras’ demands. The judge followed the approach in the Carillion decision and held that the pressure created by the threat to stop supplies was illegitimate, which meant the agreement to pay compensation was voidable.

Lawful act duress – the Supreme Court decision in Times Travel

One can only wonder if the Carillion decision would have been decided on the same basis, especially as when the demands were first made the sub-contract was yet to be signed so arguably the sub-contractor was acting lawfully, but it continued its demands after the sub-contract was signed, when the threats would have amounted to a breach of contract. This is not unusual in construction when works can start without a full formal contract in place.

Nonetheless, the Supreme Court made it clear the doctrine exists and should exist. Despite some signs of recovery from COVID 19, the current economic climate will put pressure on the supply chain and parties may well end up accepting unfavourable terms. In a small number of such cases, economic duress may still have a role to play.

This article first appeared on the Practical Law Construction blog dated 6 October 2021.

RELATED PRACTICES

This document provides a general summary and is for information/educational purposes only. It is not intended to be comprehensive, nor does it constitute legal advice. Specific legal advice should always be sought before taking or refraining from taking any action.

Commercial Construction & Engineering