Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

ISOM 654 Exam 2: Project Management Concepts and Applications, Exams of Information Systems

A comprehensive set of questions and answers covering key concepts in project management, including integration management, risk management, budgeting, and scheduling. It is a valuable resource for students preparing for exams or seeking to deepen their understanding of project management principles.

Typology: Exams

2024/2025

Available from 02/14/2025

lyudmila-hanae
lyudmila-hanae 🇺🇸

1

(2)

7.8K documents

1 / 14

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
ISOM 654 EXAM 2 WITH COMPLETE SOLUTIONS 100% VERIFIED
The process of coordinating the work and the timing of the different PM groups is called
___________. - ANSWER integration management
What is the RACI matrix? - ANSWER Responsible, Accountable, Consult & Inform
matrix
This project plan element describes both the managerial and the technical approaches
to the work. The technical discussion describes the relationship of the project to
available technologies. - ANSWER Overview
The __________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task. - ANSWER linear responsibility chart
Once the project charter is completed and the project approved, a more detailed
project plan can be developed. Which of the following issues is not addressed in the
detailed project plan? - ANSWER Developing a list of skilled workers to hire
RACI stands for - ANSWER responsible, accountable, consult, inform
A __________ must be submitted for any changes requested after the project plan has
been approved. - ANSWER change order
The process of managing risk in a project is: - ANSWER a dynamic process
throughout the project life cycle.
A useful tool for facilitating the management of changes to a projectâs scope is the -
ANSWER requirements traceability matrix
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe

Partial preview of the text

Download ISOM 654 Exam 2: Project Management Concepts and Applications and more Exams Information Systems in PDF only on Docsity!

ISOM 654 EXAM 2 WITH COMPLETE SOLUTIONS 100% VERIFIED

The process of coordinating the work and the timing of the different PM groups is called ___________. - ANSWER integration management

What is the RACI matrix? - ANSWER Responsible, Accountable, Consult & Inform matrix

This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies. - ANSWER Overview

The __________ is a specialized view of the action plan that focuses on who has what responsibility for each project task. - ANSWER linear responsibility chart

Once the project charter is completed and the project approved, a more detailed project plan can be developed. Which of the following issues is not addressed in the detailed project plan? - ANSWER Developing a list of skilled workers to hire

RACI stands for - ANSWER responsible, accountable, consult, inform

A __________ must be submitted for any changes requested after the project plan has been approved. - ANSWER change order

The process of managing risk in a project is: - ANSWER a dynamic process throughout the project life cycle.

A useful tool for facilitating the management of changes to a projectâ s scope is the - ANSWER requirements traceability matrix

Through the process of creating a WBS, the work is broken down into the lowest level tasks that are referred to as: - ANSWER packages.

This element of the project plan lists all milestone events and/or phase-gates. - ANSWER Schedule

The project launch meeting occurs when? - ANSWER Prior to beginning the project to show management commitment

The __________is a list of the project activities with major activities broken down into subactivities. - ANSWER WBS

The set of physical elements required to build a project is called the __________. - ANSWER bill of materials

Which of the following is not another name for stage gates? - ANSWER Transition points

Agile IT project teams are typically __________ and located at __________. - ANSWER small, a single site

When using a WBS, all of the work should roll up to the next level such that no extra work is required. This is referred to as the ____________________. - ANSWER 100% rule

This project plan element lists all milestone events. It identifies the estimated time for each task and is used to construct the master project schedule. - ANSWER Schedule

In a WBS, each hierarchical level should have about how many interrelated tasks? - ANSWER 2 to 20

A(n) ____________ is a network device commonly used to display project schedules. It

ANSWER Gozinto

Planning a project should result in a number of outputs. Which of the following is not one of those outcomes? - ANSWER Every possible risk is identified and a contingency plan is developed

The second (1997) Mars Pathfinder and Sojourner Rover project achieved a 94 percent cost reduction over the earlier (1976) Mars-lander mission due to: - ANSWER design-to-cost method replacing the earlier design-to-performance method.

Which cost should the project manager completely ignore in managing a project? - ANSWER Overhead and G&A

Crystal Ball is a software program that: - ANSWER provides a distribution of potential outcomes with associated probabilities

In order to develop a budget, the project manager must forecast __________. - ANSWER the resources required, when resources will be needed, the cost of resources

A budget strategy that is based on collecting the judgments and experiences of top and middle managers is referred to as the __________ approach or method. - ANSWER top-down estimating

The act of __________ is the allocation of scarce resources to the various endeavors of an organization. - ANSWER budgeting

__________ costs vary with output. - ANSWER Direct

Which of the following is not a type of quantitative risk analysis? - ANSWER expert judgment

What is always certain in projects? - ANSWER Things will not go precisely as planned.

Given a project salary cost of $400,000 per year and forecasted wage increases of 5 percent per year, calculate the non-discounted total salary cost over a three-year project lifecycle. - ANSWER $1,261,

__________ budgeting allows income and expenditures to be aggregated across projects. - ANSWER Project-oriented

The pattern of constraints in a budget embodies organizational __________. - ANSWER Policy

If a project budget is over funded, it will often __________. - ANSWER produce waste and encourage slack management

The major responsibility of professional cost estimators is to: - ANSWER reduce the level of uncertainty in cost estimates.

If projects include repetitive tasks with significant human input, the __________ rate should be factored into the cost estimate. - ANSWER learning

Overhead costs are all of the following except which one? - ANSWER Generally within the project managerâ s control

In well-understood, routine projects, such as highway construction, budgeting is: - ANSWER estimating by scaling the various cost elements based on historical data.

Which of the following is not one of the risk management subprocesses? - ANSWER work breakdown schedule

When a firm has professional cost estimators, what is their main responsibility? - ANSWER Reduce the level of uncertainty in cost estimates

___________ costs are not associated with any specific product or class of products and are typically charged as a fixed percentage of some direct cost. - ANSWER Overhead

A work element in the project plan requires 50 hours of labor each by four carpenters. The carpenters are paid $15 per hour and incur an overhead rate equal to 80 percent of their direct labor charges. The total cost would be __________ if the carpenters consume 10 percent of the workday performing personal activities. - ANSWER $5,

Identify the statement that is not correct regarding a project budget. - ANSWER The budget is not an expression of organizational policy.

___________ is involved in any forecast, though some forecasts have more than others. - ANSWER Uncertainty

Ambiguities in projects ____________________________. - ANSWER can be managed to reduce their impact

A project has three paths and a desired completion time of 43 days. The first path has a 70 percent probability of being completed in 43 days. The second has an 85 percent probability and the third haws a 90 percent probability. What is the probability that the project will be completed on time? - ANSWER 53.55 percent

The basic approach of all scheduling techniques is to form a network of activity and event relationships that graphically portrays the sequential relations between the _____ in a project. - ANSWER events

____________ on the Critical Path __________________. - ANSWER All activities; have zero slack

The following five clues can indicate when __________ scheduling is needed: late or vague progress reports, overdue deliverables, static progress indicators, longer work hours for team members, and a noticeable increase in minor âœissuesâ affecting the project. - ANSWER iterative

Any time two or more paths of a network come together, the probability of both paths being on time is the product of the probabilities for the individual paths. This scenario is referred to as __________. - ANSWER merge bias

When using the beta distribution, the denominator of the formula for standard deviation should ________. - ANSWER be approximately one-sixth of its range.

The _________ is the key input for establishing the monitoring and control systems for the project. - ANSWER schedule

Project completion probabilities computed using just the critical path are always what? - ANSWER Optimistic

The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________. - ANSWER network

In a network, if the delay of an activity will delay completion of the project, the activity is called a(n) __________. - ANSWER critical

What are some appropriate tools for managing projects? - ANSWER Crystal Ball, Microsoft Project, and Excel

__________ was developed by the U.S. Navy while the __________ was developed by __________. - ANSWER PERT, CPM, DuPont

In application, program evaluation and review technique (PERT) has primarily been used for which type of projects? - ANSWER Research and development

In AOA networks, an activity of zero duration is called a(n) ________. - ANSWER dummy activity

The most popular method for displaying a project schedule is the __________ due to ease of use and construction. - ANSWER Gantt chart

A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n) __________. - ANSWER milestone

Critical path method (CPM) has primarily been used for which type of projects? - ANSWER Construction

A task or set of tasks that are required by the project are called____________. - ANSWER activities

In PERT networks, assuming a normal distribution about estimates of duration, the âœpessimisticâ time would be where there is a _________________________. - ANSWER 1 percent chance the actual work time is greater

The GANTT Chart shows which of the following? - ANSWER Activities on Bars

Of the choices below, which tool has the most significant influence on the management of projects? - ANSWER The Schedule

__________ law suggests that work expands to fill the allotted time. - ANSWER Parkinsonâ s

The line connecting two nodes is referred to as a(n) - ANSWER arc

The methods to find an optimal solution to the constrained resource scheduling problem

fall into two categories. They are __________. - ANSWER mathematical programming and enumeration

A good rule-of-thumb is not to schedule a scarce resource for more than what percentage of capacity? - ANSWER 75-80 percent

When a project is crashed, it - ANSWER is completed in less time.

Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time. - ANSWER minimum slack first

__________ are tasks that logically follow a particular task in time. - ANSWER Successor

Goldratt illustrates that overly optimistic Project Managers are: - ANSWER very common and cause problems in scheduling.

The __________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule. - ANSWER as soon as possible

According to Goldratt: - ANSWER two activities scheduled to be carried out in parallel and using the same scarce resource are not independent.

Because the project _____ is the source of information on activity precedenceâ s, durations, and resources requirements, it is the primary input for both the project schedule and its budget. - ANSWER WBS

At any given time, a firm may have a fixed level of various resources for its projects, including: - ANSWER labor hours, equipment, and parts.

Constrained resource scheduling

The use of __________ activity time estimates may reduce the chance that crashing the project will be needed. - ANSWER three probabilistic

Important parameters used to measure effectiveness of PM scheduling include: - ANSWER schedule slippage, resource utilization, & in-process inventory.

If a contradiction or conflict between constraints is detected, __________ should always take precedence. - ANSWER technological necessities

Resource leveling aims to minimize variations in resource usage by: - ANSWER shifting tasks within their slack allowances.

The principal reason why a project manager is surprised by resource constraints on a project is the failure to include __________ in risk identification activities. - ANSWER resource availability

A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources. - ANSWER system constrained

Using the __________ heuristic method, the project team should be able to complete the maximum number of tasks during a given period of time. - ANSWER shortest task first

__________ describes the amounts of individual resources an existing schedule requires during specific time periods. - ANSWER Resource loading

Which of the following describes the amount of resources a schedule requires during specific time periods? - ANSWER Resource loading

Three important parameters used to assess the effectiveness of a scheduling system

include schedule slippage, in-process inventory, and __________. - ANSWER resource utilization

Work situations that disrupt a Project Managerâ s Schedule typically occur ______________. - ANSWER unexpectedly

In CPM, __________ are specified. - ANSWER two activity times and two costs

The tasks that logically precede a particular task in time are referred to as __________. - ANSWER predecessors

The formula for computing the cost/time slope for each activity that can be crashed is __________. - ANSWER (crash cost - normal cost) / (crash time - normal time)