Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

NERC RC BAL-005 (NERC Reliability Coordinator Examination) | Actual Questions and Answers, Exams of Electrical Engineering

NERC RC BAL-005 (NERC Reliability Coordinator Examination) | Actual Questions and Answers Latest Updated 2025/2026 (Graded A+)

Typology: Exams

2024/2025

Available from 06/29/2025

WINGS_TO-FLY
WINGS_TO-FLY 🇺🇸

1

(1)

1.1K documents

1 / 2

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
NERC RC BAL-005 (NERC Reliability Coordinator Examination) | Actual
Questions and Answers Latest Updated 2025/2026 (Graded A+)
What is the purpose of BAL-005? - ✔✔Establishes requirements for BA AGC necessary to calculate ACE
& deploy regulating reserves.
Ensures that all facilities & load electrically synchronized to the interconnection are included within the
metered boundary of a BA
What is a Balancing Authority (BA)? - ✔✔The responsible entity that integrates resource plans ahead of
time, maintains load-interchange-generation balance within a BA area & supports interconnection
frequency in real time.
What mode of AGC does NERC require BAs to operate in? - ✔✔Tie Line Bias
What is 'Regulating Capacity'? - ✔✔portion of operating reserve which is under AGC control.
What is "Regulation Service"? - ✔✔Process whereby 1 BA contracts to provide corrective response to all
or a portion of the ACE of another BA.
Controlling utility assumes the obligation of meeting all applicable control criteria as specified by NERC.
What is "Overlap Regulation Service"? - ✔✔A method of providing regulation service in which the BA
providing the regulation service incorporates another BA's actual interchange, frequency response &
schedules into providing BAs AGC/ACE equation.
What is "Supplemental Regulation Service"? - ✔✔A method of providing regulation service in which the
BA providing the regulation service receives a signal representing all or a portion of the others BA ACE.
The BAs involved will implement the service as a Dynamic Schedule.
pf2

Partial preview of the text

Download NERC RC BAL-005 (NERC Reliability Coordinator Examination) | Actual Questions and Answers and more Exams Electrical Engineering in PDF only on Docsity!

NERC RC BAL-005 (NERC Reliability Coordinator Examination) | Actual

Questions and Answers Latest Updated 202 5 /202 6 (Graded A+)

What is the purpose of BAL-005? - ✔✔Establishes requirements for BA AGC necessary to calculate ACE & deploy regulating reserves. Ensures that all facilities & load electrically synchronized to the interconnection are included within the metered boundary of a BA What is a Balancing Authority (BA)? - ✔✔The responsible entity that integrates resource plans ahead of time, maintains load-interchange-generation balance within a BA area & supports interconnection frequency in real time. What mode of AGC does NERC require BAs to operate in? - ✔✔Tie Line Bias What is 'Regulating Capacity'? - ✔✔portion of operating reserve which is under AGC control. What is "Regulation Service"? - ✔✔Process whereby 1 BA contracts to provide corrective response to all or a portion of the ACE of another BA. Controlling utility assumes the obligation of meeting all applicable control criteria as specified by NERC. What is "Overlap Regulation Service"? - ✔✔A method of providing regulation service in which the BA providing the regulation service incorporates another BA's actual interchange, frequency response & schedules into providing BAs AGC/ACE equation. What is "Supplemental Regulation Service"? - ✔✔A method of providing regulation service in which the BA providing the regulation service receives a signal representing all or a portion of the others BA ACE. The BAs involved will implement the service as a Dynamic Schedule.

What should a BA do if they are unable to calculate ACE for 30 minutes? - ✔✔Notify the RC What is the minimum scan rates for acquisition & calculation of ACE? - ✔✔At least every 6 seconds What can metering errors lead to? - ✔✔Inadvertent What is an 'Adjacent BA'? - ✔✔A BA that is interconnected to another BA either directly or via a multi- party agreement or transmission tariff. An adjacent BA does not necessarily mean a physically adjacent BA. Where is Actual Interchange measured? - ✔✔Between physically adjacent BAs What is the data retention requirement on BAs for ACE, and its components? - ✔✔ 1 year. What component of the ACE equation does a Pseudo-Tie affect? - ✔✔Net Actual Interchange (NIa) What component of the ACE equation does a Dynamic Schedule affect? - ✔✔Net Scheduled Interchange (NIs) What is the ACE equation? - ✔✔ACE = [NIa - NIs] - [(10 x (B) x (Fa - Fs)] - [Ime]