Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Percolation Tests (Falling Head), Exercises of Building Materials and Systems

2. Falling-head percolation tests determine the percolation rate of an area by filling a borehole with water and recording the rate at which it drains away. ...

Typology: Exercises

2021/2022

Uploaded on 09/27/2022

ellen.robinson
ellen.robinson 🇬🇧

4.8

(8)

222 documents

1 / 4

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Percolation Tests (Falling Head)
At least one percolation test will normally be required for every soakage device that is constructed.
Boreholes/Test Pits must be deep enough and in the correct location. The ability of the ground to accept
stormwater can vary enormously within soakage areas, even within individual properties. Because of this, at
least one percolation test will normally be required for every soakage device that is constructed.
If drilling is impossible, then percolation tests can be carried out in test pits.
Boreholes/Test Pits
Percolation tests are normally carried out in boreholes. These may be bores drilled in rock using a drilling
rig or bores drilled in soil using a hand auger or post hole auger. If drilling is impossible due to ground
conditions, then percolation tests can be carried out in test pits. Boreholes and test pits should be
constructed according to the following guidelines:
1.
Boreholes of 100 mm to 150 mm diameter should be bored to at least 1 m below the bottom of the
intended soakage device.
2.
Drilling should be continued until the permeable layer is reached where the soil is silty or has gravel
in it. The borehole/test pit base should be below, passing the clay layer to achieve effective drainage.
3.
Testpits should only be constructed if drilling is not possible. The pits should be excavated to the
level of the proposed soakage device, have a minimum base area of 1 m2 and be laid back at a
suitable angle to prevent caving-in and erosion during the test.
4.
Boreholes and test pits should be logged (that is, geological layers and soil types should be
recorded).
5.
It is advisable to perform the test during wintertime when the ground water level is high.
6.
Water-table levels should be recorded at the time of excavation (if observed). If the fieldwork is
carried out between October and May (spring autumn), winter water table levels should be
estimated at 1.0 m higher than observed water table levels.
7.
The locations of boreholes and test pits should correspond with the position of the proposed soakage
devices.
Preparation of Boreholes/Test Pits for Percolation Tests
1.
Ground conditions must emulate winter conditions.
2.
Boreholes in soil should be prepared for testing by carefully scratching the sides with a sharp-pointed
tool to remove any smeared soil surfaces and to provide a natural soil interface through which water
may infiltrate.
3.
All loose materials should be removed from the hole.
4.
If collapse of a drilled borehole seems likely, a PVC pipe should be inserted into the hole to prevent
collapse. If scouring of a test pit seems likely, about 50 mm of sand or fine gravel should be added
pf3
pf4

Partial preview of the text

Download Percolation Tests (Falling Head) and more Exercises Building Materials and Systems in PDF only on Docsity!

Percolation Tests (Falling Head)

At least one percolation test will normally be required for every soakage device that is constructed. Boreholes/Test Pits must be deep enough and in the correct location. The ability of the ground to accept stormwater can vary enormously within soakage areas, even within individual properties. Because of this, at least one percolation test will normally be required for every soakage device that is constructed. If drilling is impossible, then percolation tests can be carried out in test pits.

➢ Boreholes/Test Pits

Percolation tests are normally carried out in boreholes. These may be bores drilled in rock using a drilling rig or bores drilled in soil using a hand auger or post hole auger. If drilling is impossible due to ground conditions, then percolation tests can be carried out in test pits. Boreholes and test pits should be constructed according to the following guidelines:

  1. Boreholes of 100 mm to 150 mm diameter should be bored to at least 1 m below the bottom of the intended soakage device.
  2. Drilling should be continued until the permeable layer is reached where the soil is silty or has gravel in it. The borehole/test pit base should be below, passing the clay layer to achieve effective drainage.
  3. Testpits should only be constructed if drilling is not possible. The pits should be excavated to the level of the proposed soakage device, have a minimum base area of 1 m^2 and be laid back at a suitable angle to prevent caving-in and erosion during the test.
  4. Boreholes and test pits should be logged (that is, geological layers and soil types should be recorded).
  5. It is advisable to perform the test during wintertime when the ground water level is high.
  6. Water-table levels should be recorded at the time of excavation (if observed). If the fieldwork is carried out between October and May (spring – autumn), winter water table levels should be estimated at 1.0 m higher than observed water table levels.
  7. The locations of boreholes and test pits should correspond with the position of the proposed soakage devices.

➢ Preparation of Boreholes/Test Pits for Percolation Tests

  1. Ground conditions must emulate winter conditions.
  2. Boreholes in soil should be prepared for testing by carefully scratching the sides with a sharp-pointed tool to remove any smeared soil surfaces and to provide a natural soil interface through which water may infiltrate.
  3. All loose materials should be removed from the hole.
  4. If collapse of a drilled borehole seems likely, a PVC pipe should be inserted into the hole to prevent collapse. If scouring of a test pit seems likely, about 50 mm of sand or fine gravel should be added

to the pit to protect the bottom from scouring or sediment blinding.

  1. Holes in soil areas must be thoroughly pre-soaked to emulate winter conditions. In spring, summer or autumn (October to May), holes must be kept full for a minimum of 17 hours prior to testing. This will normally provide adequate time for the soils surrounding the hole to become saturated. During wet winter conditions, holes must be kept full for a minimum of 4 hours.
  2. Holes in rock areas must be pre-soaked to ensure that any cavities in the rock are filled before testing begins. The hydrant must be open at a high flow rate for a minimum of 10 minutes before testing begins.

➢ Falling-Head Percolation Tests

  1. Falling-head tests are most suitable for soils of medium to low permeability.
  2. Falling-head percolation tests determine the percolation rate of an area by filling a borehole with water and recording the rate at which it drains away. This test method is most suitable for use in soils with medium to low permeability.
  3. Equipment required to carry out a falling head test includes a suitable water supply, tape measure or water dipper, stopwatch, a copy of WORKSHEET 1 and pen for recording information. A torch may also be useful.

To carry out a falling head percolation test on a borehole:

  1. Thoroughly pre-soak the hole. Holes in soil areas must be thoroughly pre-soaked to emulate winter conditions. In spring, summer or autumn (October to May), holes must be kept full for a minimum of 17 hours prior to testing. This will normally provide adequate time for the soils surrounding the hole to become saturated. During wet winter conditions, holes must be kept full for a minimum of 4 hours.
  2. Fill the hole to within 0.75 m of ground level and record the drop in water level against time at evenly spaced intervals of no greater than 30 minutes, until the water level is around 0.25 m from the base of the hole or 4 hours has passed. Where the hole drains quickly, the test should be repeated several times.
  3. Graph the results according to the method on WORKSHEET 1 and derive the percolation rate in L/m2/min from the minimum slope of the curve.

➢ x is the time difference or interval between last two points in minutes.

Fill the box X with time difference between last two points. Divide Vy by AT and X to

get percolation rate P.

for “y” Percolation rate = = L/m^2 /Min Vy

AT X X

P