






















































































Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
A series of practice questions and explanations related to the pmp certification exam. It covers topics such as three point estimation using beta distribution, change management, and risk management. Designed to help individuals prepare for the pmp certification exam by providing real-world examples and explanations of key concepts.
Typology: Exams
1 / 94
This page cannot be seen from the preview
Don't miss anything!
Have you been abreast with the latest changes in the project management practices updated in the PMBOK guide - 6 th edition? If yes, here’s a chance to test your knowledge. Simplilearn’s free PMP mock exam 6 th edition is a great way to evaluate your skills on the latest project management practices. This PMP exam contains free PMP 6 th edition exam questions that are similar to the questions that you can encounter in the PMP certification exam. In an attempt to help you clear the certification exam in the first try, the PMBOK test is a great stepping stone for the all important PMP certification exam. So, why wait? Take the free PMP practice exam 6 th edition for free!
200 Questions, 240 Minutes
PMP Certification The PMP certification is the global gold standard for project management professionals. Keep abreast of the changes in the project manag ...
GO TO COURSE
®
GET 20 % DISCOUNT coupon will be auto applied.
Questions
Correct Answers
%Correct Answers
None of the above
Explanation:
The question states that you should do Three Point Estimation using Beta Distribution. The formula for this estimation technique is 4a + b + c / 6 , where a = Most Likely Estimate, b = Estimate based on Best-case scenario, and c = Estimate based on Worst-case scenario. So, the Three Point Estimate using Beta distribution is (
Explanation:
As the change has been approved, you should always update the baseline (in this case, the scope and schedule baseline) before implementing the change. This will ensure that you track performance against the new scope and schedule, and not against the old benchmarks.
Start work immediately
Ascertain the impact of this change to scope, schedule, and cost before making any change
Perform Quality Assurance
Make sure that the scope baseline and schedule baseline are updated to reflect the approved change before implementing the change
Corrective Action
Preventive Action
Defect Repair
Call Us Chat Query?
Explanation:
Defects to deliverables, corrective actions, and preventive actions need to undergo change control. So all the above statements are true except option B.
Explanation:
This is an example of Gold Plating. Integrated change control deals with formally approving or rejecting changes before they are implemented, so it is not the correct answer. Fast tracking is a schedule compression technique, so it too is not the correct answer. While Scope Creep is related to change in scope, it is related to uncontrolled changes in product or projects scope and is often due to client interference. Gold plating is done intentionally or knowingly for some strategic purpose. Here, the manager believes that by adding the extra features, future projects could be bagged.
Defects to deliverables need not undergo change control
Corrective actions need to undergo change control
Preventive actions need to undergo change control
Scope Creep
Gold Plating
Integrated Change Control
Fast Tracking
Call Us Chat Query?
Explanation:
Originally, you had 10 stakeholders to communicate with, so the number of communication channels was 10 * ( 10 - 1 ) / 2 = 4 5. However, 3 new stakeholders got added, while 1 stakeholder got reduced. So, the total number of stakeholders = 10 + 3 - 1 = 12 and hence the total number of communication channels is ( 12 * ( 12 - 1 )) / 2 = 66.
Explanation:
The most important process that could have prevented this situation would have been Scope Planning. Project deliverables are defined during scope planning, so proper implementation of this process could have prevented this situation.
Scope Planning
Scope Control
Schedule Control
Risk Monitoring and Control
Call Us Chat Query?
Explanation:
The question states that you have decided to uniquely tag each identified activity, which is nothing but Activity Identifier. This is done during creation of the Activity List.
Explanation:
Considering cross-located teams and difference in cultures, the best choice of communication in this case would be formal and written.
Schedule Network Diagram
Activity List
Milestone List
Activity Identifier
Formal and Verbal
Formal and Written
Informal and Written
Informal and Verbal
Plan Stakeholder Engagement
Call Us Chat Query?
Explanation:
Plan Stakeholder Engagement is the process to develop a strategy to effectively engage stakeholders throughout the project life cycle.
Explanation:
Here the team member is being expected to follow instructions from both the Project Manager and the Functional Manager. This is never the case in a Functional or Projectized organization where the lines of authority are clearly defined. A weak matrix organization is more like a Functional Organization where the project manager has almost no authority. The scenario explained above is typical of a balanced matrix organization where power resides equally distributed between the functional and project manager.
Identify Stakeholders
Manage Stakeholder Engagement
Control Stakeholder Engagement
Functional
Projectized
Weak Matrix
Balanced Matrix
The timing of the release of team members
The method in which you will release them
Both of the above are true
Call Us Chat Query?
Explanation:
Updating the WBS during Define Activities is often called Refinements. It occurs with riskier projects.
Explanation:
Project Quality Management addresses both the management of the project and the product. It improves project management as well as the quality of the product. It ensures that the project will satisfy customer requirements.
Refinements
Updates
Activities
Supporting detail
Address the quality of the management and product
Improve project management and the quality of the product
Ensure that the project satisfies customer requirements
All of the above
Add the additional requirements to the project plan
Ignore the request
Explain the change procedure and ask to submit a request for change
Discuss with the project team about the change
Call Us Chat Query?
Explanation:
Explaining the change procedure and asking to submit a request for change is the best choice.
Explanation:
This is an example of project incentive.
Explanation:
Options C and D are incorrect as the Backward Pass is not used to calculate the duration. In fact, the critical path is calculated based on duration. Option A talks about Early Start and Early Finish, which are calculated using Forward Pass." Using "Backward Pass
Project incentive
Project goal
Fixed price contract
None
The Early Start and Early Finish for each activity
The Late Start and Late Finish for each activity
The duration of paths other than the critical path
The duration of the critical path
Call Us Chat Query?
Explanation:
It is stated that the issues experienced in the project were ignored, so the past performance is not considered and the planned values are considered. So, the formula: EAC = AC + (BAC - EV) = 300 + ( 600 - 100 ) EAC = 800.
Explanation:
Quality Audits are meant to ascertain if the project activities conform to the policies and procedures, so it is not the correct answer. Activity Network diagrams are used for scheduling, while Process decision program charts are used to anticipate intermediate steps. The correct answer is Process Analysis, which is used to identify a problem and its cause and develop preventive actions.
Perform Quality Audits
Review Activity Network Diagrams
Lookup Process decision program charts
Process Analysis
Call Us Chat Query?
Explanation:
Why is the client being unreasonable? Why does the client want to make these changes? Obviously, your colleague is in a tough situation. However tough the problem is, a project manager must not act impulsively by seeking legal action or refuse or immediately start making the changes. When faced with a problem, a project manager should first try and find the root cause and not react. So, in this case, the best advice for your colleague would be to set up a discussion with the client and try to understand the needs of the client.
Explanation:
Once you have created the change request and submitted for approval, you don’t need to set up a separate meeting with the change control board unless asked for. Work performance reports will be shared as per agreed frequency. However, this is irrelevant to the question. You might be tempted to jump in and start work immediately, but first, the impacted baselines should be updated. In this case, all the three baselines have to be
Refuse to budge and not make any changes
Request her executive management to initiate legal action against the client
Ultimately the customer is always right, so go ahead and make the changes and absorb the impact on cost, schedule, and scope
Set up a meeting with the client to better understand the need of the changes being asked for
Get the work done immediately and start executing
Update the impacted baselines - scope, cost, and schedule
Update the work performance reports and share them with stakeholders
Set up a meeting with the change control board
Call Us Chat Query?
Explanation:
As the name suggests, Stakeholders Engagement Assessment Matrix is used to identify the current engagement level of project stakeholders. It can also be used to indicate the desired level of engagement. Through this analytical process, gaps in engagement levels can be identified and action plans and communication plans can be generated to bridge these gaps. The Stakeholder Engagement Assessment Matrix does not list stakeholders depending on their engagement level, so options C and D are clearly wrong. While you might be tempted to choose option B since you do list down all the stakeholders in a matrix in the document, the better and more qualified answer is Option A. Here, along with the complete list of stakeholders, you also indicate their current and desired engagement level.
Explanation:
The best option is to contact your company's senior management and ask for assistance.
Lists all the stakeholders along with their current engagement and desired engagement
Lists all the stakeholders
Lists only those stakeholders who are Resistant
Lists only those stakeholders who are Supportive
Forget it and don't tell anyone.
Contact your company's senior management and ask for assistance.
Ask your customer to return the gift.
Ask your customer to give you a gift which has the same cost.
Call Us Chat Query?
Explanation:
Earned Value Analysis is used to measure performance based on Scope, Schedule, and Cost.
Explanation:
All the options except Option D are true regarding scope verification. This process can also be done at the end of each project phase in the project lifecycle. So, the correct answer is option D since scope verification has nothing to do with schedule variance.
Scope and Cost
Scope and Schedule
Scope, Cost, and Schedule
Cost and Schedule
Consists of conducting inspections, reviews, and audits
Used to determine if results conform to requirements
Used to get formal sign off from clients
Used to determine schedule variance
Illustrates how various factors might be linked to potential problems or effects
Determines if a process is in control
Shows trends in a process over time
Shows the pattern of relationship between two variables
Call Us Chat Query?
The point of total assumption (PTA) is a point where cost overruns will cause a dollar for dollar decrease in profit for the seller. Hence, any subsequent cost will have to be borne by your company.
Explanation:
This is a question meant to test your understanding of change management. Any change, however small or big, should always be first analyzed for its impact on the constraints—scope, cost, and schedule—and then submitted to change control for approval. Changes without formal approval should not be implemented.
Explanation:
This is the only correct answer.
As the changes will help improve quality, execute white box testing
Create a change request
Refuse to adopt this change as this would mean a change in the agreed process
Analyze the impact of the change on scope, schedule, and cost, and then write up a Change Request
Approved Project Scope Statement, WBS, WBS Dictionary
Preliminary Project Scope Statement, Approved Project Scope Statement, WBS, WBS Dictionary
Scope Management Plan, WBS, WBS Dictionary
Scope Management Plan, Approved Project Scope Statement, WBS Dictionary
Call Us Chat Query?
Explanation:
A contract addendum needs to be signed by your company and the vendor.
Explanation:
You have avoided the risk. By interchanging the tasks, you have ensured that the resource who could go on a long vacation does not work on critical path activities. There is no question of exploiting the risk as this is not a positive risk. This is not a case of risk mitigation since you have neither created a backup plan nor come up with an alternate strategy.
A new contract needs to be signed by your company and the vendor
A contract addendum needs to be signed by your company and the vendor
An SOW needs to be signed by you and the vendor
None of the above
Mitigate the risk
Avoid the risk
Transfer the risk
Exploit the risk
Call Us Chat Query?