Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

TOM 4360 EXAM QUESTIONS AND ANSWERS 100% VERIFIED., Exams of Advanced Education

TOM 4360 EXAM QUESTIONS AND ANSWERS 100% VERIFIED

Typology: Exams

2024/2025

Available from 06/14/2025

belluna-skyler
belluna-skyler 🇺🇸

790 documents

1 / 13

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
TOM 4360 EXAM QUESTIONS AND
ANSWERS 100% VERIFIED
The scope baseline is an output of which process?
plan scope management
collect requirements
define scope
create wbs - ANSWER create wbs
We show the delay of a successor activity on a network diagram though:
lead
lag
milestone
arrow - ANSWER lag
The critical path method assumes:
no resource limitations
that resource optimization has already occurred
resource limitations
all start and finish dates are fixed - ANSWER no resource limitations
The schedule network diagram is used for which process?
estimate activity resource
develop schedule
estimate activity duration
plan schedule management - ANSWER develop schedule
which of the following is not developed as part of plan risk management:
a risk methodology
roles and responsibilities for risk management
pf3
pf4
pf5
pf8
pf9
pfa
pfd

Partial preview of the text

Download TOM 4360 EXAM QUESTIONS AND ANSWERS 100% VERIFIED. and more Exams Advanced Education in PDF only on Docsity!

TOM 4360 EXAM QUESTIONS AND

ANSWERS 100% VERIFIED

The scope baseline is an output of which process? plan scope management collect requirements define scope create wbs - ANSWER create wbs We show the delay of a successor activity on a network diagram though: lead lag milestone arrow - ANSWER lag The critical path method assumes: no resource limitations that resource optimization has already occurred resource limitations all start and finish dates are fixed - ANSWER no resource limitations The schedule network diagram is used for which process? estimate activity resource develop schedule estimate activity duration plan schedule management - ANSWER develop schedule which of the following is not developed as part of plan risk management: a risk methodology roles and responsibilities for risk management

risk register risk definitions - ANSWER Risk register the five project management process group include: initiating, planning, executing, monitoring, and controlling scope, time, cost, quality and risk initiating, planning, executing, monitoring and controlling, and closing concept, planning, execution, controlling, and closing out - ANSWER initiating, planning, executing, monitoring and controlling, and closing You are managing the development of a new medical device. Hitting the market window is critical for project success. To analyze the amount of float each activity has you will most likely use what method? crashing and expediting critical path method expert judgement resource leveling - ANSWER critical path method the cost baseline is developed as part of which process? plan cost management estimate costs determine budget control cost - ANSWER determine budget the requirements management plan is an input into which of the following processes? collect requirements define scope create WBS develop schedule - ANSWER collect requirements Projects and operations share which of the following characteristics? planned, executed, and controlled temporary

a risk methodology a risk response plan - ANSWER risk methodology

In the process of define activities we:

decompose the work packages into a hierarchy of activities decompose the activities into a list of work packages decompose the work packages into a list of activities decompose the activities into a hierarchy of work packages - ANSWER decompose the work packages into a list of activities

Resource leveling is used:

after the critical path method before the critical path method instead of critical path method instead of crashing and expediting - ANSWER after the critical path method

The requirements traceability matrix is used for:

define scope and validate scope validate scope and control scope control scope and create WBS create WBS and define scope - ANSWER validate scope and control scope

The document that defines the scheduling method and scheduling tool as well as sets the format for schedule is called:

the activity list the project schedule network diagram the schedule baseline the schedule management plan - ANSWER the schedule management plan

Examples of project schedule presentations include

activity list, bar charts, network diagram

WBS, activities, resources, dependencies

Critical path method, critical chain method

define activities, sequence activities, estimate activity resources - ANSWER activity list, bar charts, network diagram

The project charter is an input to which process group?

initiating planning executing closing - ANSWER planning

Your management has approved a contingency reserve for the project. There seems to be some confusion between contingency reserve and management reserve. You explain that management reserve is:

the difference between the max funding and the top end of the cost baseline

cost estimates added together to create an estimate for the entire project

cost estimate added together to create an estimate for meeting project requirements - ANSWER cost estimates added together to create an estimate for the entire project

the scope management plan describes

process for preparing a detailed project scope management statement

process that enables the creation of the WBS

configuration management activities

marketplace and/or other external factors affecting the project - ANSWER process for preparing a detailed project scope management statement

the vast majority of the project budget is spent during which process group?

initiating planning executing monitoring and controlling - ANSWER executing

the project budget is equal to:

value of work package cost estimates plus value of contingency reserve

value of cost baseline plus the value of the management reserve

value of the activity cost estimates plus the value of the activity contingency reserve

value of the work package cost estimates plus value of the activity contingency reserves

  • ANSWER value of cost baseline plus the value of the management reserve

the project deliverables are accepted by the customer/project sponsor as part of what process?

plan scope management validate scope define scope create WBS - ANSWER validate scope

the output of determine budget is the:

cost estimate basis of estimate cost baseline cost benefit analysis - ANSWER cost baseline

the schedule model:

is the scheduling tool populated with project data

identifies the scheduling method and scheduling tool

accept - ANSWER transfer

the project statement of work is an input to which process group?

initiating planning executing closing - ANSWER initating

example of scheduling methods include

activity list, bar chart, network diagram

WBS, activities, resources, dependencies

critical path method and critical chain method

define activities, sequence activities, estimate activity resources - ANSWER critical path method and critical chain method

examples of project schedule data or information include:

activity list, bar chart, network diagram

WBS, activities, resources, dependencies

critical path method, critical chain method

define activities, sequence activities, estimate activity resources - ANSWER WBS, activities, resources, dependencies

in the precedence diagramming method which relationship is most common?

start to start start to finish finish to start finish to finish - ANSWER finish to start

the process group that must provide feedback to implant corrective or preventive action is:

planning executing monitoring and controlling implementation - ANSWER monitoring and controlling

the scope management plan is used in all of the following processes except?

collect requirements define scope create WBS develop schedule - ANSWER develop schedule

You organization has a long and successful history as a manufacturing company. Project management has just been introduced and it is your responsibility to make sure everyone is clear on what project management is and is not. You explain that managing

approved change requests are an input into which process group?

initiating planning executing closing - ANSWER executing